30   /   10   /   2024

All welding for the wooden partition structures in Terminal-1 and Terminal-2 was carried out off-site. To ensure the safety of passengers and airport employees, as well as to avoid disrupting the operation of the existing airport, the modular systems were prefabricated off-site and then transported to the terminals for mechanical assembly and on-site installation. As a result, the airport's fire alarm systems remained inactive during the construction phase, maintaining the highest level of security throughout the process.

Terminal-1 : Completed Works

  • Dismantling of the duty-free and customs control areas.

  • Removal of existing marble, drywall, wooden walls, and electrical sub-assemblies.

  • Surveying and applications conducted with a topographer.

  • Leveling ground differences to achieve a uniform floor height using concrete wiping and smart screed application.

  • Installation of new porcelain floor coverings aligned with the airport's design concept.

  • Construction and installation of plasterboard frameworks and coatings for walls and ceilings.

  • Fabrication and mechanical assembly of statically calculated steel structures for wooden partitions.

  • Application and testing of all strong and weak current electrical systems on floors, walls, and ceilings.

  • Plastering and painting of gypsum boards on walls and ceilings within the project area.

  • Painting the entire terminal to ensure color uniformity between old and new paint on walls and ceilings.

  • Installation and commissioning of electrical panels, floor-mounted electrical socket boxes, circuit breakers, and lighting fixtures.

BAKU

AZAL AIRLINES

TERMINAL-2

30   /   10   /   2024

All welding for the wooden partition structures in Terminal-1 and Terminal-2 was carried out off-site. To ensure the safety of passengers and airport employees, as well as to avoid disrupting the operation of the existing airport, the modular systems were prefabricated off-site and then transported to the terminals for mechanical assembly and on-site installation. As a result, the airport's fire alarm systems remained inactive during the construction phase, maintaining the highest level of security throughout the process.

Terminal-2 : Completed Works

  • Dismantling of the customs control area

  • Dismantling the existing linoleum on the ground in the project area.

  • Making topography and surveys and applications

  • Bringing the places in different codes to the code by deleting the method and applying a smart screed.

  • Plasterboard carcass and coating works on walls and ceilings

  • Making statically calculated steels for wooden partitions by mechanical assembly method

  • Application and testing of all strong and weak current electrical systems on floors, walls, ceilings.

  • Plastering and painting of gypsum boards on walls and ceilings in the project area.

  • Paint works of existing walls and ceilings in the project area.

  • Installation and commissioning of electrical panels, floor-standing electrical socket boxes, circuit breakers and lighting products.